1. CITY HALL:   7651 E. Central Park Avenue
  1. Phone: 316-744-2451
  1. Hours: M-Th: 8:00 AM-5:30 PM, F: 8:00 AM-1 PM
Bel Aire Logo
Search

News Flash

Street Replacement Starting 5/16

City News and Information Posted on May 15, 2025

Starting tomorrow, May 16, APAC will begin full-depth street replacement work on Perryton. This will involve removing the affected road sections and installing a five-inch rock base. Crews will work diligently to complete the base installation by the end of the day, though work may continue into Saturday, May 17, if needed.

The replacement work on Stratford between Odessa and Perryton kicked off yesterday.

APAC anticipates that crews will return next Wednesday, May 21, to start laying asphalt in the area, weather permitting.

During construction, the road will remain drivable, and residents will have access to their driveways. To minimize traffic and ensure the safety of workers, we encourage all other drivers to use alternate routes if possible.


Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow